1/6/12(friday afternoon)....dossier was rcvd at CCAI
Monday 1/9/12....Review began
Thurs 1/12..Critical review done, translation began
Friday 1/13/12....translation complete, sent to CCCWA
Monday 1/16/12...dossier rcvd in China
Tuesday 1/17/12....LID
Tuesday 2/21/12...LOA
Thursday 2/23/12 sent signed LOA back to CCAI
Friday 2/24/12...CCAI rcvd LOA and I-800 etc and sent to NBC
Saturday 3/10/12...rcvd I800 PA
Monday 3/19/12...CCAI e-mailed NVC letter to China
Tuesday 4/3/12...Article 5 issued
Monday 4/23/12... Travel Approval rec'd